Thursday, August 28, 2008 ::  

  Corporate Profile
  Services
  Experiences
  Business Clients
  Locations
  Links
  Technical Paper
  Press Release
  Feedback
Ongoing Projects
Design & Procurement Support for CKP Mercury Removal Unit

Client :

CARIGALI HESS OPERATING COMPANY

Total Manhour : Base Scope – 31,612
Optional Scope – 4,452
Project Location : The Cakerawala field is located in Block A-18, approximately 150 km NE of Kota Bharu and approximately 100 km south of the Bongkot field in approximately 55 m of water in the Malaysia-Thailand Joint Development area
Scope of work undertaken by MMC O&G : Click here for details
Project Duration : 5 Months (October 24th 2007 – March 21st 2008)
Weight : N/A
     
Conceptual & Detailed Design of St. Joseph Re-Development Project

Client :

Main Contractor: MMC OIL & GAS ENGINEERING SDN BHD
Owner: SHELL SARAWAK BERHAD

Total Manhour : N/A
Project Location : Located at Usukan Bay at North East of Labuan
Scope of work undertaken by MMC O&G : Click here for details
Project Duration : Total 12 months: Conceptual 4 mths, Detailed Design 8 mths
Weight : N/A
     
DETAILED DESIGN ENGINEERING SERVICES FOR MURPHY GAS PLANT 1

The main onshore processing equipment includes inlet separators, compressors, gas dehydration units, scrubbers, fiscal metering and a chiller. Besides the processing plant; a workshop, warehouse and office building will be part of the overall facilities.

Client : MURPHY OIL CORPORATION
Total Manhour : 72, 194hrs
Project Location : Located in Bintulu (Onshore), Sarawak – Murphy Gas
Plant 1
Scope of work undertaken by MMC O&G : The scope of work will be Detailed Design. This scope encompasses preparation of Detailed Design Engineering Services package for an onshore receiving facility Murphy Gas Plant #1 in Bintulu, Sarawak . The new onshore receiving facility will be located approximately 500 meter northeast of the existing MLNG – 3 plants. It will receive saturated gas from three (3) offshore fields (i.e. Serampang, Merapuh & Golok) via two (2) 24” subsea pipelines.
Project Duration : Detailed Design: 8 months (May 07 to Dec 07)
Weight : N/A
     
PC 4 GAS DEVELOPMENT PROJECT

which is located approximately 148km offshore Bintulu at a water depth of 79 meters in block SK310. The first gas is expected in Q3 2008. Two (2) wells will be drilled, each is expected to produce up to 200 mmscfd. Gas production at plateau of 220 mmscfd is anticipated from PC4 field.

Gas production from PC4 will be tied back to B11 hub via a 12” pipeline for a distance of 25km. The gas will be metered prior to going into B11 processing facilities. B11 is jointly owned by (Sarawak Shell Berhad) SSB and PCSB with 50:50 ownership and operated by SSB.

PC4 field will be developed on a fast-track basis with the following facilities:
i) Unmanned minimum facilities platform with 2 single completion wells
ii) Inter-platform Pipeline (about 25 km pipeline of size 12” to B11)
iii) Host Tie-In activities at B11, E11 and BOCC

Client : PETRONAS CARIGALI SDN BHD
Total Manhour : 40,000 (Base scope)
15,000 (Optional scope)
Project Location : Block SK310, Bintulu.
Scope of work undertaken by MMC O&G : FEED and Detailed Design.
Project Duration : 21 weeks
Weight : Topside = 870mT
Flare Tower = 193mT
Jacket = 1160mT
Pile = 1430mT
Conductor = 390mT
Total weight = 4043mT

ENGINEERING, PROCUREMENT, CONSTRUCTION & COMMISSIONING OF ADDITIONAL PSR-2 CRUDE STORAGE TANKS PROJECT

Malaysian Refining Corporation Sdn Bhd (MRCSB) the owner of refining complex PSR-2 in Mukim Sungai Udang, Tangga Batu,Melaka intends to construct Two (2)additional of floating roof crude tanks. MMCOG and Warga Hikmat have formed a consortium to undertake the EPCC of the tanks. Other works include installation of new piping system and fire fighting facility such as foam system, water spray system and fire detection system. When completed by end of 2008, each tank will be capable of storing 500,000 barrels of crude oil as feedstock to PSR2.

Client : MALAYSIAN REFINING COMPANY SDN BHD
Total Manhour : 5,500 hrs
Project Location : Petronas Penapisan Melaka Sdn Bhd, Sg. Udang, Melaka
Scope of work undertaken by MMC O&G : Engineering and Procurement
Project Duration : Approximately 26 months
Weight : N/A

 

ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING OF JABUNG GAS BOOSTER STATION AT JAMBI, SUMATERA, REPUBLIC OF INDONESIA

PT Transportasi Gas Indonesia (TGI) is the operator of the Grissik-Duri (Sumatera, Indonesia) and Grissik-Singapore gas pipelines. The natural gases are produced from ConocoPhillips Blocks at Grissik, Caltex Block at Duri and PetroChina Block at Jabung. The natural gas is gathered, treated and then transported by 28-inch pipeline for sale to Singapore via Batam. Due to increase of sale gas flow, TGI will install a booster compressor station at Jabung, which is located in the province of Jambi, Sumatera, Indonesia to boost up the pipeline pressure.

A consortium of companies led by MMCOG was awarded the EPCC contract. The project scope constitutes gas booster compressor and utilities as well as accommodation for the operators. The Facility are designed for up to 4 numbers of Solar Taurus 70 Gas Turbine Compressors including Control Building housing the integrated DCS and ESD system (also known as ICSS System) and a utilities facility supplying plant and instrument air, water treatment system, fire fighting and detection system. The potable water is from the bore hole from underground wells and the electrical power supply will solely from the plant generator sets. There will be three (3) gas engines driven generator sets and one (1) emergency diesel engine driven generator set to supply power to the facilities.

The accommodation building with all amenities such as dining hall, laundry room, gymnasium, tennis court etc will also be provided.

The project is scheduled to be completed and commissioned by December 2008

Client : PT. TRANSPORTASI GAS INDONESIA
Total Manhour : 48,000 (Engineering Portion)
Project Location : Province of Jambi, Sumatera Selatan, Republic of Indonesia
Scope of work undertaken by MMC O&G : Engineering, Procurement, Construction and Commissioning (EPCC)
Project Duration : Approximately 24 months
Weight : N/A
Engineering Design Services for Angsi Phase IV-TCOT Crude Oil Pipeline
The main purpose of this work order is to ensure that all crude produced by Angsi fields as well as from the other Peninsular Malaysia fields can be transported to TCOT in the event of Ta-P-TCOT pipeline failure or vice versa. This will provide 100& security of crude supply to Peninsular Malaysia.

Main activities:
i) Add additional 26 inch crude pipeline with associated topside facilities and pipeline riser from AnDR-A going to TCOT.
ii) The existing TCOT receiving facilities will be upgraded in order to cater for this new 26-inch pipeline and tie-in. This pipeline is expected to function as alternate crude evacuation pipeline for the existing 24 inch crude pipeline from Ta-P to TCOT.
iii) Upgrade on the existing 16 inch pipeline with associated modification and upgrade on existing launching facilities at AnDR-A and receiving facilities at Ta-P will be required and it is expected that current unidirectional pipeline flow will be converted to bi-directional flow to enable crude coming from Ta-P to flow to Angsi Complex or vice versa.

Client : PETRONAS CARIGALI SDN BHD
Total Manhour : N/A
Project Location : Located at offshore Terengganu, Peninsular Malaysia
Scope of work undertaken by MMC O&G : The scope of work will be Front End Engineering Design (FEED) and Detailed Design. This scope will include the upgrading at AnDR-A and new off take pipeline to TCOT.
Project Duration : FEED : 3 months (July 06 to October 06)
Detailed Design : 6 months ( October 06 to March 07)
Weight : N/A