Monday, August 03, 2015      Login     Contact Us
 

News & Events

  • MMC Oil & Gas Engineering secures engineering contract in Bintulu

    MMCOG opened its Bintulu branch office after being awarded the Provision of Engineering Services via Bintulu-based Design Office (BDO) for Malaysia LNG Sdn Bhd (MLNG) on Oct 30, 2014...
    2015-07-06 11:36
  • Majlis Kesyukuran dan Doa Selamat 2015

    Majlis Kesyukuran dan Doa Selamat telah dilangsungkan pada 11 Jun 2015, bersamaan dengan 24 Syaabna 1436H (Khamis)
    2015-06-24 16:22
  • MMCOG at OGA 2015

    OGA is a show for the regional market and major players in the industry alike. Top prominent officials from PETRONAS was also present at the exhibition to meet and mingle.
    2015-06-09 17:45
  • MMCOG Badminton Tournament 2015

    The Badminton Tournament at JJB Court, Setapak on 23rd May 2015 where JDT become champions beating the Gladiators with 2-0 scoreline in the final, while PDRM secure 3rd place.
    2015-06-09 16:01
  • MMCOG Bowling Tournament 2015

    Our annual bowling tournament was held on the 18th April 2015 with up to 120 players joining the event. The winners are Kiwi (group), Serindit (women high series) and Cenderawasih (men high series).
    2015-05-08 10:27

Our services


Last Updated: Thursday, July 9, 2015 - 09:49

Detailed Design & Engineering Services For Baram South Development project

The project was awarded by Petronas Carigali Sdn Bhd (PCSB)in July 2003 for the Detailed Design services of three (3) platforms which is located approximately 25 km offshore Lutong, Sarawak.It comprises Compression & Production Platform (BAKP-B), Wellhead Platform (BAJT-H) and Wellhead Platform (BAJT-I), as well as the associated Pipelines tie-ins to the existing BAK-B and BAP-B platforms.

Period: 7/2003 - 10/2004
Total Manhours: 90,000
Weight: BAJT-H & BAJT-I 2100 MT , BAKP-B 5900 MT

The project was awarded by Petronas Carigali Sdn Bhd (PCSB) to MMC Oil & Gas Engineering Sdn Bhd in July 2003 for the Detailed Design services of three (3) platforms which is located approximately 25 km offshore Lutong, Sarawak. It comprises Compression & Production Platform (BAKP-B), Wellhead Platform (BAJT-H) and Wellhead Platform (BAJT-I), as well as the associated Pipelines tie-ins to the existing BAK-B and BAP-B platforms. BAJT-I is linked to BAJT-H via 10" multiphase pipeline/6" gaslift pipeline. While, BAJT-H is linked to BAKP-B via another separate multiphase/ gaslift pipeline for processing facilities at BAKP-B. A temporary 16-man shelter is located at BAKP-B. Detailed Design was completed in May'04, with AFC drawings finalized in October'04.

Facilities Description

• Water Depth ranges from 12m to 61m
• New BAKP-B bridge-linked to existing BAK-B
• 6-legged structure for BAKP-B, 4-legged structure for BAJT-H & BAJT-I
• Designed to produce 160 MMscfd of export gas and 55 MMscfd lift gas
• Designed for 25,000 bpd crude oil production
• Designed to SIPROD mode of operation and catering to jackup & rigup conditions.
• Design Life to 25 years
• Platform is expected to be in operation by 4th Quarter 2005.