Friday, June 23, 2017      Login     Contact Us
 

News & Events

  • Hjh. Sharifah Zaida Nurlisha – Winner TOP 50 Female Energy Player In Emerging Economies (ASIA)

    Hjh. Sharifah Zaida Nurlisha is the General Manager of projects in MMC Oil & Gas Engineering Sdn. Bhd. and also the first elected female President of the Malaysian Oil and Gas Services Council (MOGSC).
    2017-06-13 10:14
  • Majlis Kesyukuran & Bacaan Yassin 2017

    Jemputan Majlis Kesyukuran dan Bacaan Yassin
    2017-05-22 14:54
  • Birthday Celebration for Staffs

    As per our proud tradition for our employees, MMCOG held its' quarterly birthday celebration and gathering for its employees for the first quarter of 2017.
    2017-05-05 10:42
  • MLNG Jewel Run 2017

    A hearty congratulations to all finishers at the recently concluded The MLNG Jewel Run 2017 was held on 21st January 2017 at University Putra Malaysia Bintulu Campus.
    2017-02-27 15:36
  • CEO Info Session 2017

    successfully commemorate our Ceo Info Session 2017, which was held on 8 February 2017, Wednesday at level 1 Menara Tokyo Marine. The event started at 4.00 pm and ended at 5.30 pm.
    2017-02-15 13:18

Our services

Last Updated: Thursday, June 22, 2017 - 12:40


Detailed Design & Engineering Services For Baram South Development project

The project was awarded by Petronas Carigali Sdn Bhd (PCSB)in July 2003 for the Detailed Design services of three (3) platforms which is located approximately 25 km offshore Lutong, Sarawak.It comprises Compression & Production Platform (BAKP-B), Wellhead Platform (BAJT-H) and Wellhead Platform (BAJT-I), as well as the associated Pipelines tie-ins to the existing BAK-B and BAP-B platforms.

Period: 7/2003 - 10/2004
Total Manhours: 90,000
Weight: BAJT-H & BAJT-I 2100 MT , BAKP-B 5900 MT

The project was awarded by Petronas Carigali Sdn Bhd (PCSB) to MMC Oil & Gas Engineering Sdn Bhd in July 2003 for the Detailed Design services of three (3) platforms which is located approximately 25 km offshore Lutong, Sarawak. It comprises Compression & Production Platform (BAKP-B), Wellhead Platform (BAJT-H) and Wellhead Platform (BAJT-I), as well as the associated Pipelines tie-ins to the existing BAK-B and BAP-B platforms. BAJT-I is linked to BAJT-H via 10" multiphase pipeline/6" gaslift pipeline. While, BAJT-H is linked to BAKP-B via another separate multiphase/ gaslift pipeline for processing facilities at BAKP-B. A temporary 16-man shelter is located at BAKP-B. Detailed Design was completed in May'04, with AFC drawings finalized in October'04.

Facilities Description

• Water Depth ranges from 12m to 61m
• New BAKP-B bridge-linked to existing BAK-B
• 6-legged structure for BAKP-B, 4-legged structure for BAJT-H & BAJT-I
• Designed to produce 160 MMscfd of export gas and 55 MMscfd lift gas
• Designed for 25,000 bpd crude oil production
• Designed to SIPROD mode of operation and catering to jackup & rigup conditions.
• Design Life to 25 years
• Platform is expected to be in operation by 4th Quarter 2005.