Sunday, May 31, 2015      Login     Contact Us
 

News & Events

  • MMCOG Bowling Tournament 2015

    Our annual bowling tournament was held on the 18th April 2015 with up to 120 players joining the event. The winners are Kiwi (group), Serindit (women high series) and Cenderawasih (men high series).
    2015-05-08 10:27
  • CEO Info Session 2015

    We had just successfully commemorate our CEO Info Session 2015 which was held on the 17th April 2015(Friday) at level 23 Menara Tokyo Marine. The event started at 2.30PM and ended at 5.00 PM.
    2015-05-08 09:55
  • Arbitration Talk by Wong & Partners

    Wong & Partners held a talk at MMCOG detailing on the use of arbitration for the energy, mining & infrastructure industry.
    2015-05-08 09:38
  • MMCOG received Bentley's "Be Inspired" finalists' award

    On behalf of MMC Oil & Gas Engineering Sdn Bhd, our director, Ir. Mohamad cordially received the “Be Inspired" certificate award from Bentley's CEO Greg Bentley...
    2015-03-20 17:47
  • BDO Official Contract Signing Ceremony

    On the 10th of February 2015, MMCOG and MLNG officially signed for the opening of MMCOG's first Bintulu Design Office.
    2015-02-26 15:44

Our services


Last Updated: Thursday, May 21, 2015 - 11:10

Detailed Design & Engineering Services For Baram South Development project

The project was awarded by Petronas Carigali Sdn Bhd (PCSB)in July 2003 for the Detailed Design services of three (3) platforms which is located approximately 25 km offshore Lutong, Sarawak.It comprises Compression & Production Platform (BAKP-B), Wellhead Platform (BAJT-H) and Wellhead Platform (BAJT-I), as well as the associated Pipelines tie-ins to the existing BAK-B and BAP-B platforms.

Period: 7/2003 - 10/2004
Total Manhours: 90,000
Weight: BAJT-H & BAJT-I 2100 MT , BAKP-B 5900 MT

The project was awarded by Petronas Carigali Sdn Bhd (PCSB) to MMC Oil & Gas Engineering Sdn Bhd in July 2003 for the Detailed Design services of three (3) platforms which is located approximately 25 km offshore Lutong, Sarawak. It comprises Compression & Production Platform (BAKP-B), Wellhead Platform (BAJT-H) and Wellhead Platform (BAJT-I), as well as the associated Pipelines tie-ins to the existing BAK-B and BAP-B platforms. BAJT-I is linked to BAJT-H via 10" multiphase pipeline/6" gaslift pipeline. While, BAJT-H is linked to BAKP-B via another separate multiphase/ gaslift pipeline for processing facilities at BAKP-B. A temporary 16-man shelter is located at BAKP-B. Detailed Design was completed in May'04, with AFC drawings finalized in October'04.

Facilities Description

• Water Depth ranges from 12m to 61m
• New BAKP-B bridge-linked to existing BAK-B
• 6-legged structure for BAKP-B, 4-legged structure for BAJT-H & BAJT-I
• Designed to produce 160 MMscfd of export gas and 55 MMscfd lift gas
• Designed for 25,000 bpd crude oil production
• Designed to SIPROD mode of operation and catering to jackup & rigup conditions.
• Design Life to 25 years