Wednesday, July 30, 2014      Login     Contact Us
 

News & Events

  • MMC Iftar 2014

    As per annual tradition, MMC held its MMC Iftar 2014 at Mahkota II & III Ballrooms, Hotel Istana Kuala Lumpur. The event which lasted from 6:00 pm onwards on 9 July 2014, was also joined by the...
    2014-07-21 11:46
  • CEO Info Session 2014

    We had just successfully commemorate our CEO Info Session 2014 which was held on the 22nd May 2014(Thursday) at level 23 Menara Tokyo Marine. The event started at 2.00PM and ended at 5.00 PM.
    2014-05-26 17:36
  • Management Committee Meeting (MCM) Lunch & Farewell Ceremony

    Management Committee Meeting (MCM) had its fourth gathering and meeting on the 16th April 2014. In conjunction with the ceremonial lunch, it is also an event to warmly send-off...
    2014-04-18 17:40
  • MMC O&G bidding for RM700m contracts

    MMCOG as appeared on multiple presses' business coverage in conjunction with OTC 2014 event. Excerpted: MMC Corp Bhd's unit MMC Oil and Gas (O&G) Engineering Sdn Bhd is bidding for contracts worth RM 700 million domestically and abroad to grow its revenue by 200 percent to RM300 million a year from 2018.
    2014-04-01 17:55
  • OTC Asia 2014

    The inaugural Offshore Technology Conference (OTC) 2014, organised by 13 sponsoring societies, brings industry professionals to Asia's oil and gas hub to meet, share knowledge, and discover cutting-edge technologies. OTC Asia is a must-attend event, offering a peer-selected technical programme which focuses on the full spectrum of offshore technology in drilling, exploration, production, and environmental protection.
    2014-04-01 11:59

Our services


Last Updated: Monday, July 21, 2014 - 12:18

Detailed Design & Engineering Services For Baram South Development project

The project was awarded by Petronas Carigali Sdn Bhd (PCSB)in July 2003 for the Detailed Design services of three (3) platforms which is located approximately 25 km offshore Lutong, Sarawak.It comprises Compression & Production Platform (BAKP-B), Wellhead Platform (BAJT-H) and Wellhead Platform (BAJT-I), as well as the associated Pipelines tie-ins to the existing BAK-B and BAP-B platforms.

Period: 7/2003 - 10/2004
Total Manhours: 90,000
Weight: BAJT-H & BAJT-I 2100 MT , BAKP-B 5900 MT

The project was awarded by Petronas Carigali Sdn Bhd (PCSB) to MMC Oil & Gas Engineering Sdn Bhd in July 2003 for the Detailed Design services of three (3) platforms which is located approximately 25 km offshore Lutong, Sarawak. It comprises Compression & Production Platform (BAKP-B), Wellhead Platform (BAJT-H) and Wellhead Platform (BAJT-I), as well as the associated Pipelines tie-ins to the existing BAK-B and BAP-B platforms. BAJT-I is linked to BAJT-H via 10" multiphase pipeline/6" gaslift pipeline. While, BAJT-H is linked to BAKP-B via another separate multiphase/ gaslift pipeline for processing facilities at BAKP-B. A temporary 16-man shelter is located at BAKP-B. Detailed Design was completed in May'04, with AFC drawings finalized in October'04.

Facilities Description

• Water Depth ranges from 12m to 61m
• New BAKP-B bridge-linked to existing BAK-B
• 6-legged structure for BAKP-B, 4-legged structure for BAJT-H & BAJT-I
• Designed to produce 160 MMscfd of export gas and 55 MMscfd lift gas
• Designed for 25,000 bpd crude oil production
• Designed to SIPROD mode of operation and catering to jackup & rigup conditions.
• Design Life to 25 years
• Platform is expected to be in operation by 4th Quarter 2005.