Thursday, March 23, 2017      Login     Contact Us
 

News & Events

  • MLNG Jewel Run 2017

    A hearty congratulations to all finishers at the recently concluded The MLNG Jewel Run 2017 was held on 21st January 2017 at University Putra Malaysia Bintulu Campus.
    2017-02-27 15:36
  • CEO Info Session 2017

    successfully commemorate our Ceo Info Session 2017, which was held on 8 February 2017, Wednesday at level 1 Menara Tokyo Marine. The event started at 4.00 pm and ended at 5.30 pm.
    2017-02-15 13:18
  • Tahlil & Doa Selamat untuk Tahun 2017

    MMCOG telah menjayakan Majlis Bacaan Tahlil & Doa Selamat sempena kesyukuran, dan kedatangan tahun 2017 pada 5 Januari 2017, pada waktu Zohor di surau aras 19...
    2017-01-09 16:17
  • Blood Donation Campaign 2016

    In accordance to World Blood Donor Day in June, MMCOG also held a Blood Donation Campaign in September to support the notion...
    2016-10-28 16:28
  • MOGSEC 2016

    The 3rd Malaysia Oil & Gas Services Exhibition & Conference was a huge success. Throughout MOGSEC 2016, MMCOG along with other companies and Oil Giant PETRONAS have given overwhelming support...
    2016-10-05 16:52

Our services

Last Updated: Monday, March 6, 2017 - 09:42


FEED for BlockSK309 & SK311 East Cluster Gas Development Project

 MMCOG as the main contractor provided engineering services to Murphy Sarawak Oil Co. Ltd for marginal gas development in Block SK309 and SK311, offshore Bintulu, Sarawak. The SK Phase 3 Gas Development comprised of non-associated gas (NAG) development from South Acis, Wangsa and the East Cluster fields comprising the East Patricia, Tiram and Sapih fields.

The latter fields are located to the east of the major PCSB / Shell operated trunk pipelines and are planned to be developed as one project to capitalize on the economies of scale and to reduce overall development cost. This document covers the FEED scope of work for the East Cluster fields i.e. East Patricia, Tiram and Sapih fields under SK Phase 3 Gas Development.

Scope of Work
MMCOG as the main contractor covered the scope of work as described under the following main work breakdown structures:

1. DESIGN CONCEPT MANAGEMENT
•    Design Management
•    Basis of Design and Concept Drawings (based from Wangsa)
•     Assistance for Preliminary Cost Estimates
•    Basic Design Production Plan
•    On-going review and challenge session

2. FRONT END ENGINEERING DESIGN (FEED)
•    Design Management
•    Basic Design Work Pack
•    Tender Package
•    Final Cost Estimates
•    Produced Final FEED Documents

Client

:Murphy Sarawak Oil
Project Location:Malaysia
Project Duration:4 Months (Completed on Feb 2015)
Project No.:MURPHY-A-2373U