Saturday, December 10, 2016      Login     Contact Us
 

News & Events

  • Blood Donation Campaign 2016

    In accordance to World Blood Donor Day in June, MMCOG also held a Blood Donation Campaign in September to support the notion...
    2016-10-28 16:28
  • MOGSEC 2016

    The 3rd Malaysia Oil & Gas Services Exhibition & Conference was a huge success. Throughout MOGSEC 2016, MMCOG along with other companies and Oil Giant PETRONAS have given overwhelming support...
    2016-10-05 16:52
  • MMCOG Corporate Office Aidil Fitri 2016

    Sempena Hari Raya Aidil Fitri 2016, di atas kerjasama sepakat staf-staf MMCOG Corporate Office telah mengadakan Majlis Keramaian dan Makan-Makan...
    2016-08-15 17:38
  • CEO Info Session 2016

    Successfully commemorated our CEO Info Session 2016 which was held on the 18th May 2016 (Wednesday) at level 23 Menara Tokyo Marine. The event started at 3.00PM and ended at 5.00 PM.
    2016-06-15 15:42
  • Majlis Tahlil & Doa Selamat 2016

    MMCOG telah menjayakan Majlis Bacaan Tahlil & Doa Selamat sempena menyambut Ramadhan pada 1 Jun 2016, bersamaan 24 Shaaban 1437H.
    2016-06-07 13:09

Our services

Last Updated: Friday, October 28, 2016 - 16:28


RUBY-A (RBDP-A) Gaslift Project

MMC Oil & Gas Engineering Sdn Bhd was awarded the contract to provide engineering support by PTSC (Vietnam) as part of the latter’s fabrication work of Ruby-B (RBDP-B) Topsides for Petronas Carigali Vietnam (PCV).

Period: 1/2004 - 6/2005
Total Manhours: Ruby A : 14,000 Ruby B:15,000
Weight:

RUBY-A (RBDP-A) Gaslift Project

Ruby field is located approximately 155km offshore Vung Tau, SR Vietnam in Blocks 01 and 02, in water depth of about 50m. Pilot phase production from Ruby field commenced on 22 October 1998 with the field facility consisting of a wellhead platform RBDP-A, a Floating, Processing, Storage and Offloading vessel (FPSO Ruby Princess) and a 100 subsea pipeline which transports the unstabilised crude from the platform RBDP-A to the FPSO Ruby Princess. Ruby Drilling Platform A (RBDP-A) Gaslift Project presents the basis for the design and installation of a mini gaslift compressor and associated facilities and tie in work at the host platform RBDP-A and FPSO, RUBY PRINCESS.

PROVISION OF POST AFC ENGINEERING DESIGN FOR RUBY-B (RBDP-B) TOPSIDES FABRICATION
MMC Oil & Gas Engineering Sdn Bhd was awarded the contract to provide engineering support by PTSC (Vietnam) as part of the latter’s fabrication work of Ruby-B (RBDP-B) Topsides for Petronas Carigali Vietnam (PCV). Included in the scope of work is the completion of detailed engineering previously prepared to be completed to an Approved for Construction (AFC) status and to verify and conduct design checks. Also included in the scope of work is vendor data review and vendor data incorporation of major equipment and piping items and to provide response and technical advice to technical queries. MMC Oil & Gas Engineering Sdn Bhd provided and set up a site team at RBDP-B project office in Vung Tau, Vietnam.

Facilities Description

• Provide response and technical advice on site queries.
• Provide continuous supervision and coordination which include design activities, supervision of the project team and planning of work scope to achieve the required technical standard and satisfactory project completion within budget and schedule.
• Provide inter discipline checks for integration and clashes.
• Weight control and weight report to determine actual weight and final center of gravity location.
• Review vendor data, interface with Vendor and provide vendor data incorporation for compliance with overall process requirements for the platform.
• Review and update engineering documents and drawings.
• Provide review, comments and updating on the AFC packages.