Thursday, March 23, 2017      Login     Contact Us
 

News & Events

  • MLNG Jewel Run 2017

    A hearty congratulations to all finishers at the recently concluded The MLNG Jewel Run 2017 was held on 21st January 2017 at University Putra Malaysia Bintulu Campus.
    2017-02-27 15:36
  • CEO Info Session 2017

    successfully commemorate our Ceo Info Session 2017, which was held on 8 February 2017, Wednesday at level 1 Menara Tokyo Marine. The event started at 4.00 pm and ended at 5.30 pm.
    2017-02-15 13:18
  • Tahlil & Doa Selamat untuk Tahun 2017

    MMCOG telah menjayakan Majlis Bacaan Tahlil & Doa Selamat sempena kesyukuran, dan kedatangan tahun 2017 pada 5 Januari 2017, pada waktu Zohor di surau aras 19...
    2017-01-09 16:17
  • Blood Donation Campaign 2016

    In accordance to World Blood Donor Day in June, MMCOG also held a Blood Donation Campaign in September to support the notion...
    2016-10-28 16:28
  • MOGSEC 2016

    The 3rd Malaysia Oil & Gas Services Exhibition & Conference was a huge success. Throughout MOGSEC 2016, MMCOG along with other companies and Oil Giant PETRONAS have given overwhelming support...
    2016-10-05 16:52

Our services

Last Updated: Monday, March 6, 2017 - 09:42


Provision of FEED and EPCIC of Kasawari Gas Development Project

MMCOG worked with Saipem Sapura Kencana for the Kasawari Gas Development Project entailing the main objectives of WHP ready for Rig (RFR ) as well as First Gas Date (FGD) within 15 to 33 months from effective date.

The Kasawari gas field was discovered in November 2011 within a water depth of approximately
108m at the center.

The Kasawari Field is located in Block SK316 within the Central Luconia Province (See Figure 1 below),
approximately 200km North of Bintulu, Sarawak - Malaysia. The Kasawari gas field was discovered
in November 2011 within a water depth of approximately 108m at the center.

Figure 1 Location of Kasawari Field

 

Figure 2 Overall Kasawari Gas Development Project

As shown in the figure 2 above, MMCOG's role was to provide engineering design for the facilities of Kasawari which include:

  • Central Processing platform (CPP) – 8-legged
  • 9-slot Wellhead platform (WHP) – 4-legged
  • Flare structures – tripod
  • Bridges (CPP to WHP and CPP to Flare structure)

Client

:Saipem & Sapura Kencana
Project Location:Malaysia
Project Duration:8 Months (project completion on Jan 2015)
Project No.:SSK-A-2314